√ complete
removal of roofing without
interruption to tenants’ and neighboring companies’ operations,
with limited
roof access
√ maintaining
the utmost safety of tenants,
the public, and the contracting teams
working on a 13-story, highly sloped,
curved roof
√ moving
construction scaffolding, equipment, and new supplies (and removing
debris material) through
the building to minimize disruption to downtown commerce and
increase safety (Fabri-Tech hoisted the bulk of the seamless
panels on a single weekend
day; daily traffic was conducted through the building) |
|
√ working
overnight (increasing lighting
and safety issues) to minimize daytime business interruptions and
prepare the
roof segments for the daylight installation team
√ performance
in harshest winter weather
conditions
√ value-engineering
materials
√ analysis
and timing to counteract steel
market volatility
√ precise
planning for maximum benefit at
minimum cost |